Nerja council have announced that the contract to complete the pedestrianisation of El Barrio has been signed and that this final phase of the construction will start soon, possibly as early as next week.

The work to pedestrianise and replace the drains and other services was started at the end of 2011, with the first stage completed before summer 2012. The last stage of the work is expected to take less than four months, and should be finished before the start of the summer season.

El Barrio is the street that runs west from Plaza Cavana (next to the Balcon de Europa) towards Torrecilla beach.

Once El Barrio has been finished, the next street due to be pedestrianised is Calle Diputacion, which is the street parallel to El Barrio.